Paver Calculator
Pavers, pallets, compacted base, bedding sand, joint sand and cost for a patio or driveway
To find how many pavers you need, divide the area by the space one paver covers and add 5 to 15% for cuts, depending on the pattern. A 12 × 16 ft patio (192 sq ft) in 4 × 8 in pavers takes 864 pavers, or 951 with 10% for herringbone. Underneath go a compacted gravel base, at least 4 in for a patio and 6 in for a driveway, and 1 in of bedding sand.
Last updated October 2026
Method: Pavers = area × 144 ÷ (length × width) for nominal sizes, or ÷ ((length + joint) × (width + joint)) for actual sizes, plus a cut allowance by pattern. Base tons = base area × compacted depth ÷ 27 × 2.0 tons per compacted cubic yard, the 4,000 lb per cubic yard factor Ohio DOT uses for crushed stone base compacted in place. Base area adds the ICPI extension past the edge restraint. Bedding sand is 1 in screeded (ICPI) at 1.35 tons per cubic yard plus 10%; polymeric sand comes from the joint volume at 100 lb per cubic foot plus 10%. Both sand weights sit inside the range the U.S. Army's FM 5-434 gives for loose dry sand.
Included: Rectangles, circles and L-shapes; pavers with and without cuts; pallets; base in cubic yards, tons and 50 lb bags; bedding sand; polymeric sand bags; edge restraint length; dig depth; and a material cost total.
Not included: Geotextile, drain pipe, sub-base or stabilized base for poor soils, permeable paver aggregates, steps and walls, delivery, equipment rental and labor. Piece counts and pallet sizes for a specific brand come from its spec sheet.
📐 Patio area
Those edges need no edge restraint, and the base does not run past them.
🧱 Pavers and pattern
ICPI calls for joints between 1/16 and 3/16 in. Most pavers have spacer bars that set it for you.
🪨 Base and sand
Minimum compacted base on well-drained soil (CMHA, formerly ICPI): 4 in for patios and walks, 6 in for residential driveways. Cold climates and wet or weak soils need a thicker base, so follow local standards there.
Bedding sand is figured at a screeded 1 in. Base weight uses 2.0 tons per compacted cubic yard, sand 1.35 tons per cubic yard.
💵 Prices
Example prices only. Replace them with your local quotes.
🧱 Pavers to buy (with 10% for cuts)
🪨 Base, sand and edging
| Compacted gravel base, 4 inover 212.0 sq ft, incl. 6 in past the edging | 2.62 yd³5.23 tons · or 210 bags of 50 lb |
| Bedding sand, 1 in screededconcrete sand, plus 10% | 0.65 yd³0.88 tons |
| Polymeric joint sandjoints filled to 1/8 in below the top, plus 10% | 4 bags183.7 lb |
| Edge restraintperimeter 56.0 ft, minus rigid edges | 40.0 ft |
| Dig depth below the finished surfacebase + paver + 1 in sand, less 3/8 in settlement | 7.00 in |
💵 Material cost estimate
| Pavers (211.3 sq ft) | $739.67 |
| Base gravel (5.23 tons) | $235.56 |
| Bedding sand (0.88 tons) | $44.00 |
| Polymeric sand (4 bags) | $120.00 |
| Edge restraint (40.0 ft) | $100.00 |
| Total materials | $1,239.22 |
Delivery fees, geotextile, equipment rental, sealer and labor are not included.
Paver calculator: pavers, base and sand for a patio or driveway
A paver patio is a stack of layers: pavers on a 1 in bed of sand, over a compacted gravel base, locked in by edge restraints, with sand swept into the joints. Each layer is bought in a different unit (pieces, tons, bags and linear feet), which is why a materials list is easy to get wrong. This paver calculator sizes all of them from one set of measurements and adds a cost line for each.
For an odd-shaped yard, break the area into rectangles with the Square Footage Calculator first. If you would rather pour than lay, the Concrete Calculator sizes a slab of the same footprint.
How many pavers: the formula
Every paver claims its own face plus its share of the joints around it. Paver sizes are usually quoted as nominal sizes: a "4 × 8" concrete paver measures about 3.94 × 7.87 in (100 × 200 mm), and the spacer bars on its sides fill out the rest of the 4 × 8 module. For nominal sizes the count is:
Pavers per sq ft = 144 ÷ (L × W) Pavers to buy = Area (sq ft) × pavers per sq ft × (1 + cut allowance) If you know the true face size instead, add the joint to each side: pavers per sq ft = 144 ÷ ((L + J) × (W + J)). ICPI's construction guide calls for joints between 1/16 and 3/16 in. A spec sheet settles the question, because it lists the pieces per square foot for that exact product; tumbled pavers with smaller faces, for example, can run above the count the nominal size suggests.
Worked example: a 12 × 16 ft patio against the house
A patio runs 16 ft along the back wall of the house and 12 ft out into the yard, paved with 2-3/8 in thick 4 × 8 pavers in a 90° herringbone, on a 4 in base:
- Area: 12 × 16 = 192 sq ft; perimeter 56 ft, of which 16 ft is the house wall
- Pavers: 192 × 4.5 = 864, plus 10% for herringbone cuts = 951 pavers (211.3 sq ft, or 2.11 pallets at 100 sq ft each)
- Edge restraint: 56 − 16 = 40 ft; the house wall does that job on the fourth side
- Base area: 192 + 40 × 0.5 ft extension = 212 sq ft
- Base: 212 × 4 ÷ 12 = 70.67 cu ft = 2.62 cu yd × 2.0 = 5.23 tons
- Bedding sand: 192 × 1 ÷ 12 = 16 cu ft = 0.59 cu yd, plus 10% = 0.65 cu yd, or 0.88 tons
- Polymeric sand: 167.0 lb of joint, plus 10% = 183.7 lb, so 4 bags of 50 lb
- Dig depth: 4 in of base + 2-3/8 in paver + 1 in sand − 3/8 in settlement = 7 in below the finished surface
With the example prices in the calculator ($3.50 per sq ft of pavers, $45 per ton of base, $50 per ton of sand, $30 per bag of polymeric sand and $2.50 per ft of edging), the materials come to $739.67 + $235.56 + $44.00 + $120.00 + $100.00 = $1,239.22, about $6.45 per square foot. The 2.11 pallets mean two full pallets plus a partial one, which many yards sell by the piece.
Worked example: an L-shaped driveway
A driveway runs 40 ft from the street, widening to 20 ft at a parking pad, so it measures 40 × 20 ft overall with a 20 × 10 ft corner left as lawn. It meets the garage slab and the street apron along 30 ft of concrete, uses 6 × 9 pavers in a 45° herringbone, and sits on an 8 in base because the soil is clay and the winters are cold:
- Area: 40 × 20 − 20 × 10 = 600 sq ft; perimeter 2 × (40 + 20) = 120 ft
- Pavers: 144 ÷ 54 = 2.667 per sq ft, so 1,600 pavers, plus 15% = 1,840 pavers (690 sq ft, 6.9 pallets)
- Edge restraint: 120 − 30 = 90 ft
- Base area: an 8 in base extends 8 in past the edging, so 600 + 90 × 0.667 = 660 sq ft
- Base: 660 × 8 ÷ 12 = 440 cu ft = 16.30 cu yd, or 32.59 tons, placed and compacted in two 4 in lifts
- Bedding sand: 2.04 cu yd with the allowance, 2.75 tons; polymeric sand 426.1 lb, 9 bags
- Dig depth: 8 + 3 = 11 in
At the same example prices the materials total $4,514.17, of which the base alone is $1,466.67. That is typical for driveways: the stone under the pavers is a bigger share of the job than on a patio, and at 32.6 tons it arrives as truckloads, not bags.
Pavers per 100 sq ft by size
The table applies the formula to the six most common US sizes. The first columns treat the size as nominal; the last column shows the count if the same numbers were the actual face size with a 1/8 in joint added. Cut allowances are rounded up to whole pavers.
| Size (in) | Per sq ft | Per 100 sq ft | +5% | +10% | +15% | Actual + 1/8 in |
|---|---|---|---|---|---|---|
| 4 × 8 | 4.50 | 450 | 473 | 495 | 518 | 429.7 |
| 6 × 6 | 4.00 | 400 | 420 | 440 | 460 | 383.8 |
| 6 × 9 | 2.67 | 266.7 | 280 | 294 | 307 | 257.6 |
| 12 × 12 | 1.00 | 100 | 105 | 110 | 115 | 97.9 |
| 16 × 16 | 0.5625 | 56.25 | 60 | 62 | 65 | 55.4 |
| 24 × 24 | 0.25 | 25 | 27 | 28 | 29 | 24.7 |
Reading the nominal size as actual costs 1 to 5% in the count, most for small pavers: 450 against 429.7 per 100 sq ft for 4 × 8. The cut allowance covers that gap on most jobs, but on a large patio the spec sheet's pieces per square foot is the number to trust.
Paver base calculator: depth and tons
The base carries the load, so it gets the most attention in ICPI's Tech Spec 2, now published by the Concrete Masonry & Hardscapes Association as Tech Note PAV-TEC-002. Patios, sidewalks and other pedestrian areas need at least 4 in of compacted base over well-drained soil, residential driveways at least 6 in, and parking lots and residential streets at least 8 in. Colder climates and continually wet or weak soils require a thicker base, and very weak or saturated soils may call for a base stabilized with cement or asphalt; local standards or an engineer set the exact depth there. The base should be dense-graded aggregate (crusher run or road base), spread and compacted in lifts of 4 to 6 in to at least 98% of standard Proctor density.
Because the depth you design is the compacted depth, the calculator weighs the base at 2.0 tons per compacted cubic yard, the 4,000 lb per cubic yard conversion factor Ohio DOT applies to crushed stone aggregate base compacted in place. Loose in the pile, stone weighs less per yard: the U.S. Army's earthmoving manual (FM 5-434) lists dry gravel at 2,700 to 3,000 lb per loose cubic yard, or 1.35 to 1.5 tons. If your yard sells by the loose cubic yard you therefore need a third to a half more yards than the compacted volume; the loose column below uses 1.5 tons, so treat it as the minimum. The table gives the base for every 100 sq ft of base area:
| Compacted depth | Cu yd | Tons at 2.0 | 50 lb bags | Loose cu yd at 1.5 t (minimum) | ICPI extension |
|---|---|---|---|---|---|
| 4 in | 1.23 | 2.47 | 99 | 1.65 | 6 in |
| 6 in | 1.85 | 3.70 | 149 | 2.47 | 6 in |
| 8 in | 2.47 | 4.94 | 198 | 3.29 | 8 in |
| 10 in | 3.09 | 6.17 | 247 | 4.12 | 10 in |
| 12 in | 3.70 | 7.41 | 297 | 4.94 | 10 in |
The extension column is ICPI's rule for how far the base runs past the edge restraint: 6 in for bases up to 6 in deep, a distance equal to the depth from 6 to 10 in, and 10 in beyond that. It keeps the edging spikes in solid stone instead of soil, which matters most where the ground heaves in winter. The bag column shows why bags only suit small jobs: even a 4 in base needs about one 50 lb bag per square foot.
Bedding sand and polymeric joint sand
The bedding layer is concrete sand meeting ASTM C33, screeded to an uncompacted 1 in. ICPI is specific about what not to use: masonry sand, limestone screenings and stone dust. Screenings and stone dust often do not compact uniformly and can keep water from draining sideways through the bedding layer. Never use extra sand to fill low spots in the base, because the dip reappears in the pavers. Every 100 sq ft takes 0.31 cubic yards, or 0.34 cubic yards and 0.46 tons with the 10% allowance the calculator adds for screeding losses. The tons use 2,700 lb per cubic yard, inside the 2,600 to 2,900 lb the Army's FM 5-434 lists for loose dry sand.
The joints get a finer sand meeting ASTM C144, or a polymeric sand whose binder hardens after it is wetted. The calculator figures polymeric sand from the joint volume, filled to 1/8 in below the paver surface at 100 lb per cubic foot, the same dry-sand weight as above. For 2-3/8 in thick pavers, the net weight per 100 sq ft is:
| Size (in) | 1/16 in joint | 1/8 in joint | 3/16 in joint |
|---|---|---|---|
| 4 × 8 | 43.7 lb | 87.0 lb | 129.8 lb |
| 6 × 6 | 38.9 lb | 77.3 lb | 115.4 lb |
| 6 × 9 | 32.4 lb | 64.6 lb | 96.4 lb |
| 12 × 12 | 19.5 lb | 38.9 lb | 58.1 lb |
| 16 × 16 | 14.6 lb | 29.2 lb | 43.7 lb |
| 24 × 24 | 9.8 lb | 19.5 lb | 29.2 lb |
In bags, that puts one 50 lb bag at about 57 sq ft of 4 × 8 pavers with 1/8 in joints, 129 sq ft of 12 × 12 units and 257 sq ft of 24 × 24 slabs. Bag labels give coverage ranges by joint width and paver size, and they are worth comparing with these figures before you buy. Thicker 3-1/8 in pavers have deeper joints: 116.0 lb per 100 sq ft for 4 × 8 at 1/8 in.
Patterns and cut waste
The pattern decides how many pavers end up as offcuts. Running bond and stack bond meet a straight edge square, so cuts are few; the calculator's default for them is 5%. A 90° herringbone meets the edge with a zigzag that needs a cut every other paver, so its default is 10%. A 45° herringbone runs diagonally to every edge and wastes the most, so the default is 15%. These are planning allowances, not a standard, so raise them for a layout with many cuts. ICPI recommends herringbone for all vehicular areas because the interlock resists tires starting, braking and turning. Gaps wider than 3/8 in along the edge should be filled with cut pieces, and on driveways no cut piece should be smaller than a third of a paver. Circles and curved borders add cutting to any pattern, so add about 5% for them.
Edge restraints and dig depth
Edge restraints keep the pavers from spreading apart, and ICPI's Tech Spec 3 treats them as essential. Aluminum, steel, plastic made for pavers, and concrete all work, as do the walls of a building and an existing slab, which is why the calculator subtracts those edges. Soil backfill and garden-bed edging are not acceptable restraints, and the restraint must touch at least 1 in of the paver's side. The calculator's edging figure is the perimeter minus the rigid edges you enter.
The dig depth follows from the layers. ICPI sets the top of the base 3 in below the finished surface for 2-3/8 in pavers on 1 in of sand, which leaves 1/4 in for compaction settling and 1/8 in for minor settling over time. Add the base depth and you have the excavation: 7 in for a 4 in patio base, 11 in for an 8 in driveway base, and 3/4 in more with 3-1/8 in pavers. Slope the dig and the base at least 1.5 to 2% (about 1/4 in per foot) away from the house.
How to use this calculator, and who it is for
- Choose the shape and enter its dimensions in feet. For an L, measure the full rectangle and then the unpaved corner.
- Enter rigid edges, the feet of patio that meet a wall, a garage slab or a curb.
- Pick the paver size and say whether it is nominal or the actual face size, then set the joint.
- Pick the pattern, which fills in a cut allowance you can overwrite.
- Set the thickness, base depth and pallet coverage, and leave the ICPI base extension on unless the base is already in place.
- Enter your prices and read the results: pavers and pallets in the headline, then base, sand, edging, dig depth and a cost table.
Homeowners use it to price a patio before asking for bids and to order the base in one delivery instead of two. Landscapers use the per-100 sq ft tables for quick takeoffs and the cost table to explain a quote line by line. It also helps anyone choosing between paver sizes, since the count, cuts and joint sand change with every option.
Key terms
- Nominal size: the paver's trade size, which includes the joint; the face is slightly smaller.
- Dense-graded base: crushed stone with fines (crusher run, road base) that compacts into a stable layer; graded under ASTM D2940.
- Lift: one layer of base spread and compacted before the next, 4 to 6 in with a plate compactor.
- Bedding sand: the 1 in layer of ASTM C33 concrete sand the pavers are set on.
- Polymeric sand: joint sand with a binder that hardens when wetted, resisting washout and weeds.
- Edge restraint: the border that holds the pavers together, spiked into the base.
- Base extension: the strip of base that runs past the edge restraint to support it.
- ASTM C936: the US paver standard, requiring an average compressive strength of at least 8,000 psi and absorption of no more than 5%.
What changes the result, and tips
- Base depth moves the biggest number: going from 4 to 6 in raises the base by half, and the dig with it.
- Paver size changes the count and the joint sand, not the base. Small pavers mean more pieces and more joint per square foot.
- Pattern adds 5 to 15% to the paver order, more with curves.
- Rigid edges cut both the edging and the base extension, so enter the house wall and any slab you build against.
- Order base and sand for delivery together, and keep them separate on site; base mixed into bedding sand ruins the screed.
- Pull pavers from several bundles at once, as ICPI advises, so slight color differences blend across the patio.
Limitations
The calculator assumes level, firm subgrade and a single base layer of dense-graded aggregate. Poor soils may need geotextile, a sub-base of larger stone or a stabilized base, and permeable pavers use open-graded stone and no sand at all. The densities are typical values: real base weighs more when wet and less when it holds little fines, so ask the quarry for its figure. Piece counts follow the size you enter, while a brand's spec sheet lists the exact pieces per square foot and per pallet. Steps, seat walls, borders of a different paver and the corners of the base extension (about 1 sq ft each) are not counted.
Related calculators
For a gravel path or the stone around the patio, the Gravel Calculator and the Stone Calculator size loose aggregate by depth. The Sand Calculator handles bulk sand for other jobs, and the Concrete Calculator covers a poured footing, curb or slab. Use the Square Footage Calculator for areas made of several rectangles, and if the project moves indoors, the Grout Calculator sizes grout and thinset for tile.
Sources
- Concrete Masonry & Hardscapes Association (CMHA, which absorbed ICPI), Tech Note PAV-TEC-002-22, Construction of Interlocking Concrete Pavements (formerly ICPI Tech Spec 2, revised 2022): paver thickness, base depths, lifts and compaction, bedding sand, joint widths, patterns, cuts, saw dust and utility marking.
- CMHA, Tech Note PAV-TEC-003-22, Edge Restraints for Interlocking Concrete Pavements (formerly ICPI Tech Spec 3, revised 2022): restraint types, base extension and base elevation below the finished surface.
- CMHA, PAV-MAN-006-20, Construction Tolerances for ICP (ICPI guide revised February 2020): base extension table, minimum base thickness, aspect ratio, slope, herringbone for vehicular areas and cut pavers.
- Ohio Department of Transportation, Construction and Material Specifications, Item 304 Aggregate Base, Table 304.07-1: 4,000 lb per cubic yard for crushed stone and crushed gravel base, measured compacted in place.
- U.S. Department of the Army, FM 5-434, Earthmoving Operations (June 2000, PDF copy), Table 1-2: loose weights of dry sand (2,600 to 2,900 lb per cubic yard) and dry gravel (2,700 to 3,000 lb).
- U.S. Occupational Safety and Health Administration, 29 CFR 1926.1153, Respirable crystalline silica: Table 1 controls for handheld power saws.
- National Institute of Standards and Technology (NIST), unit conversion: cubic feet, cubic yards and tons.
- ASTM International: C936 (solid interlocking concrete paving units), C33 (concrete aggregates, bedding sand), C144 (masonry sand, joint sand) and D2940 (graded aggregate for bases).
⚠️ Common mistakes & edge cases
Ordering a compacted depth by loose volume
A 4 in base over 192 sq ft is 2.37 compacted cubic yards, but plate compaction squeezes loose stone hard. At 1.5 tons per loose cubic yard, 2.37 yards is 3.56 tons, about a quarter short of the 4.74 tons the compacted layer actually holds.
Stopping the base at the paver edge
Edging spiked into soil moves, and the pavers follow it. ICPI wants the base to run past the restraint by its own depth for most patios and driveways; on the 12 × 16 ft example that adds 20 sq ft of base and half a ton of stone.
Mixing up nominal and actual sizes
Treating a nominal 4 × 8 as an actual 4 × 8 with a 1/8 in joint gives 429.7 pavers per 100 sq ft instead of 450, about 4.5% fewer. Check whether the size on the box is nominal and switch the calculator to match.
Bedding pavers in stone dust or masonry sand
Both are on ICPI's list of materials never to use for bedding. Stone dust in particular tends to compact unevenly and keeps water from draining through the bedding layer, so the pavers settle in patches. Ask for ASTM C33 concrete sand.
Leveling a lumpy base with extra sand
A thick spot of bedding sand settles more than a thin one, so every hollow you fill with sand comes back as a dip in the pavers. Fix the base until it is within 3/8 in under a 10 ft straightedge, then screed a uniform 1 in.
Using large slabs on a driveway
A 24 × 24 in unit that is 2-3/8 in thick is about 10 times as long as it is thick, far past ICPI's 4 to 1 limit for driveways. Keep slabs on patios and walks, and use 4 × 8 or 6 × 9 pavers in herringbone where cars drive.
❓ Frequently asked questions
How many pavers do I need?
Divide the area by the space one paver covers, then add a cut allowance for the pattern. With nominal sizes, pavers per square foot = 144 / (length x width in inches), so 4 x 8 in pavers run 4.5 per sq ft. A 12 x 16 ft patio is 192 sq ft, which takes 864 pavers before cuts, 908 with 5% for running bond, and 951 with 10% for a 90 degree herringbone.
How many square feet does a pallet of pavers cover?
It depends on the paver's size, thickness and brand, so use the square feet or pieces per pallet on the supplier's spec sheet. The calculator's 100 sq ft is only a starting value. Thicker 80 mm (3-1/8 in) pavers weigh more per square foot than 60 mm (2-3/8 in) units, so a pallet of them usually covers less. Enter your supplier's coverage and the calculator does the division, showing both the exact pallet count and the number of whole pallets.
How much paver base do I need?
Multiply the base area in square feet by the compacted depth in feet, divide by 27 for cubic yards, and multiply by about 2.0 tons per compacted cubic yard. A 192 sq ft patio with a 4 in base is 2.37 cubic yards or 4.74 tons. Extending the base 6 in past the 40 ft of edging, as ICPI recommends, raises it to 2.62 cubic yards or 5.23 tons.
How deep should the gravel base be under pavers?
The industry construction guide (CMHA Tech Note PAV-TEC-002, formerly ICPI Tech Spec 2) sets a minimum compacted base of 4 in for patios, sidewalks and other pedestrian areas over well-drained soil, and 6 in for residential driveways. Colder climates and continually wet or weak soils require a thicker base, and very weak or saturated soils may need a base stabilized with cement or asphalt. Spread and compact the base in lifts of 4 to 6 in with a plate compactor rather than all at once.
How much sand do I need for pavers?
Pavers sit on bedding sand screeded to an uncompacted 1 in. Each 100 sq ft needs 0.31 cubic yards, or 0.34 cubic yards and 0.46 tons with a 10% allowance at 1.35 tons per cubic yard. Use concrete sand meeting ASTM C33, not masonry sand or stone dust. The joints take a separate, finer joint sand or polymeric sand.
How many bags of polymeric sand do I need?
It depends on the joint width, the paver size and the paver thickness. For 2-3/8 in thick 4 x 8 pavers with 1/8 in joints filled to 1/8 in below the top, each 100 sq ft holds about 87 lb, so a 50 lb bag covers roughly 57 sq ft. A 192 sq ft patio needs 167 lb, or 4 bags with a 10% allowance. Larger pavers have less joint per square foot and need fewer bags.
Which paver pattern should I use for a driveway?
Use a herringbone pattern, either 45 or 90 degrees. ICPI recommends herringbone for all vehicular applications because the interlocking joints resist the creep caused by tires starting, braking and turning. Running bond is fine for patios and walkways and wastes fewer pavers to cuts. Common planning allowances, and the calculator's defaults, are about 5% for running bond, 10% for 90 degree herringbone and 15% for 45 degree herringbone; a layout with many cuts needs more.
Can I use 12 x 12 or 24 x 24 pavers on a driveway?
Usually not. ICPI recommends that an interlocking paver be no more than 4 times as long as it is thick for pedestrian areas and driveways. A 4 x 8 in paver that is 2-3/8 in thick is about 3.4 to 1, but a 12 x 12 in unit of the same thickness is about 5 to 1 and a 24 x 24 in unit about 10 to 1, which makes them paving slabs. Slabs suit patios and walkways; under cars they tend to crack and rock.
How many pavers do I need for a 12 ft circle?
A 12 ft circle covers 113.1 sq ft. With 4 x 8 in pavers at 4.5 per sq ft that is 509 pavers before cuts. Curved edges need more cutting, so plan 15% for a herringbone field with a curved border: 586 pavers. The edging runs 37.7 ft around the circle, and a 4 in base with the ICPI extension takes about 3.26 tons.
How much do the materials for a paver patio cost?
Add up five lines: pavers, base gravel, bedding sand, joint sand and edge restraint. For the 12 x 16 ft example with example prices of $3.50 per sq ft of pavers, $45 per ton of base, $50 per ton of sand, $30 per bag of polymeric sand and $2.50 per ft of edging, the materials total $1,239.22, about $6.45 per square foot of patio. Delivery, equipment rental and labor come on top.
💡 Good to know
A compacted cubic yard of base weighs about 2 tons
That is the figure Ohio DOT uses to convert crushed stone base between weight and compacted volume: 4,000 lb per cubic yard. One ton of base therefore covers about 40 sq ft at 4 in deep, or 27 sq ft at 6 in.
Cut pavers wet
Concrete pavers contain crystalline silica, and ICPI notes that saw dust from them carries high levels of it. Under OSHA's construction standard, a handheld saw needs an integrated water feed to the blade; outdoors, that alone covers up to 4 hours of cutting a day, beyond which a respirator is required.
Call before you dig
A 7 to 11 in excavation reaches buried cables and irrigation lines. ICPI's construction guide says to have utilities marked first, at least two days before digging. Across the US the request goes through one phone number, 811, and state rules on the notice period vary.